HFR repairs progressing according to planConcrete removal startedRadiation protection during the repairs |
![]() The huts on the site of the High Flux Reactor. ![]() The last pieces of Densimet are being positioned on the floor of the basin. ![]() The concrete upper shield is fitted above the reactor basin. |
HFR repairs progressing according to planThe repairs to the High Flux Reactor are proceeding well and according to plan. There have been, no safety incidents during the period and the radiation dose levels for internal and external employees has remained below the planned limits. |
![]() A replica of the reducer is being placed in the mockup. ![]() The mockup prior to the casting of the concrete. ![]() The mockup has been made of the same concrete as the original HFR floor. |
Concrete removal startedThe reducers of the High Flux Reactor that are to be repaired are located within a very thick concrete floor. This concrete must be removed to allow the repairs to be carried out. This civil engineering phase of the repair was started on Friday 9 April. As Civil Sub Project Manager, Edwin Bach is closely involved with the preparation and the execution of the ‘concrete part’ of the repair. The removal and replacement of the heavy concrete around the Bottom Plug Liner has been extensively tried and tested in recent months. “We made a replica from the same concrete as that of the original HFR floor at the premises of the main contractor Strukton,” explains Bach. “We practised drilling into this and also assessed the quality of the new concrete. We carried out a casting test on the site, using the new low-compaction heavy concrete in a mock-up.” The demolition work is particularly complicated because the concrete must be removed from underneath, so the demolishion team have to work above their heads. Investigation revealed that core-drilling is the most suitable method of concrete removal. In the space of four weeks, more than two hundred cores are drilled out from under each of the the reducers, then the remaining concrete is removed with a special hammer. During the work, the drills are cooled with water, which must be removed after careful monitoring. The very last pieces will be chipped away with an electric hand drill . |
![]() Placing of the support framework in the subpile room. ![]() Preparations for the drilling. ![]() The drilling of the first hole. |
Radiation protection during the repairsIn the past year, part of the project organisation has been the preparation of the radiation protection precautions necessary for the HFR repair. Many of these documents and directives are part of the existing NRG Health and Safely structure, but a number have been specially prepared for this repair. Local Radiation Safety Officer Joop Lutgerink: “We started with a base document in which we included the task risk analysis for the actual repairs as well as the preparations, the test repairs and the commissioning and restart of the Reactor. In addition, documents were also drafted, for example, for the Technical Specifications for the radiation shielding and the legally required Health and Safety Plan for all staff”. During the whole repair period, around forty external workers will come on to the site. To ensure the safety of these people, a number of special radiation safety directives are in force. All new external workers receive comprehensive training on their first day. During their work they are watched over continuously by an NRG supervisor. “To make all this possible, we also trained our own personnel so that they know what their duties and responsibilities are,” states Lutgerink. “As well as the Health and Safety Plan mentioned earlier, we prepared additional safety regulations for third parties. These cover subjects such as work permits and emergency situations and also indicate what our sanctions are if the safety rules are breached.” Both the individual radiation dose levels of workers and the collective dose for each task are being accurately recorded in a dose register. Lutgerink: “We take responsibility for the safety of our internal and external employees and the environment. In practice, the plan will be continuously monitored and any improvements implemented if required; as we have made good preparations we have the scope to do this.” |








